Posted on: February 28, 2018

North Atherton Street Project

This page is your one-stop-shop for all the latest updates on the Pennsylvania Department of Transportation’s North Atherton Street Project.

My Post


Project Overview

Download the following map to see the tentative timeline of the North Atherton Street Project. 

Atherton Construction Schedule v 2.0


Download


The PennDOT project page can be found at www.penndot.gov/AthertonStreet.

Update 09/10/2018

Weather Forces Schedule Changes on Atherton Street Job

The Pennsylvania Department of Transportation (PennDOT) wants to keep the public informed about the work that continues on North Atherton Street. Other than the long-term lane closures between West North Hills Place and Cherry Lane that are listed below, there will be no lane closures beginning Friday, September 14 through Sunday, September 15, due to a Pennsylvania State University home football game. Two lanes will be open for inbound traffic and two lanes open for outbound traffic throughout that period of time. The center lane will remain closed and no left turns will be allowed.

Please note the other following delays through Friday, September 14:

  • From West Aaron Drive to West North Hills Place – No work anticipated during this period.
  • From West North Hills Place to West Cherry Lane – Due to the development of a sinkhole, the Northland Center entrance will be closed until repairs can be made sometime this week. This entrance is about 300-feet prior to Blue Course Drive on the right side of Atherton Street heading toward the University. A long-term traffic pattern remains in place closing the far, right lane heading toward the University. When the contractor is not working, two lanes will remain open for inbound and outbound traffic. However, when the contractor is working, traffic will be reduced to a single lane for inbound traffic. Due to the turning lane being used for inbound traffic, left turns will always be restricted through the length of this work zone.
  • From West Cherry Lane to West Hillcrest Avenue – The contractor will be installing a new water line in this section. When the contractor is working, there will one lane closed in each direction. Please note that West Cherry Lane will be closed from Wednesday, September 12 through Thursday, September 13. A detour around this closure will be established using North Atherton Street, Blue Course Drive and Martin Street.

All work is weather and schedule dependent. Travel delays can occur because of the lane closures—especially during high traffic volume. Drivers should allow for extra travel time and use caution when traveling through work zones. Flaggers may be present in the roadway directing traffic and traffic may be stopped for short periods of time. Drivers are encouraged to be patient and courteous to other drivers.

PennDOT has numerous projects taking place in the State College area and is aware of the frustration road work can create. This work is part of the North Atherton Street project that is taking place through 2019 with phased work zones stretching from Aaron Drive to Park Avenue. Work will include the relocation of numerous utility lines, relocation of sewer and water lines, drainage improvements, curbing, sidewalks, ADA ramps, traffic signal upgrades, new concrete median and paving.

To help make decisions about travel, motorists are encouraged to “Know Before You Go” by visiting www.511PA.com. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1.


Update 09/07/2018

Update through Mid-September on North Atherton Street Project

The Pennsylvania Department of Transportation (PennDOT) wants to keep the public informed about the work that continues on North Atherton Street. Other than the long-term lane closures between West North Hills Place and Cherry Lane that listed are below, there will be no lane closures beginning Friday, September 14 through Sunday September 15, due to a Pennsylvania State University home football game. Two lanes will be open for inbound traffic and two lanes open for outbound traffic throughout that period of time. The center lane will remain closed and no left turns will be allowed.

Please note the other following delays through Friday, September 14:

  • From West Aaron Drive to West North Hills Place – No work anticipated during this period.
  • From West North Hills Place to West Cherry Lane – A long-term traffic pattern remains in place closing the far, right lane heading toward the University. When the contractor is not working, two lanes will remain open for inbound and outbound traffic. However, when the contractor is working, traffic will be reduced to a single lane for inbound traffic. Due to the turning lane being used for inbound traffic, left turns will always be restricted through the length of this work zone.
  • From West Cherry Lane to West Hillcrest Avenue – The contractor will be installing a new water line in this section. When the contractor is working, there will one lane closed in each direction. Please note that West Cherry Lane will be closed from Monday, September 10 through Wednesday, September 12. A detour around this closure will be established using North Atherton Street, Blue Course Drive and Martin Street.

All work is weather and schedule dependent. Travel delays can occur because of the lane closures—especially during high traffic volume. Drivers should allow for extra travel time and use caution when traveling through work zones. Flaggers may be present in the roadway directing traffic and traffic may be stopped for short periods of time. Drivers are encouraged to be patient and courteous to other drivers.

PennDOT has numerous projects taking place in the State College area and is aware of the frustration road work can create. This work is part of the North Atherton Street project that is taking place through 2019 with phased work zones stretching from Aaron Drive to Park Avenue. Work will include the relocation of numerous utility lines, relocation of sewer and water lines, drainage improvements, curbing, sidewalks, ADA ramps, traffic signal upgrades, new concrete median and paving.

To help make decisions about travel, motorists are encouraged to “Know Before You Go” by visiting www.511PA.com. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1.

Update 08/30/2018

Update through September 7 on North Atherton Street Project

The Pennsylvania Department of Transportation (PennDOT) wants to keep the public informed about the work that continues on North Atherton Street.

Please note, other than the long-term lane closure between West North Hills Place and Cherry Lane, there will be no lane closures beginning Friday, August 31, due to a Pennsylvania State University home football game, and Monday, September 3, due to the Labor Day holiday. Two lanes will be open for inbound traffic and two lanes open for outbound traffic throughout that period of time. The center lane will remain closed and no left turns will be allowed.  

People traveling on North Atherton Street can expect the following delays through Friday, September 7:

  • From West Aaron Drive to West North Hills Place – No work anticipated during this period.
  • From West North Hills Place to West Cherry Lane – A long-term traffic pattern remains in place closing the far, right lane heading toward the University. When the contractor is not working, two lanes will remain open for inbound and outbound traffic. However, when the contractor is working, traffic will be reduced to a single lane for inbound traffic. Due to the turning lane being used for inbound traffic, left turns will always be restricted through the length of this work zone.  
  • From West Cherry Lane to West Hillcrest Avenue – No work anticipated by the contractor during this period.  However, Verizon will continue to perform relocation work. Traffic control will consist of daylight lane closures maintaining traffic to at least one lane each direction.

There will be NO LANE CLOSURES from Friday, August 31 through Monday, September 3. 

All work is weather and schedule dependent. Travel delays can occur because of the lane closures—especially during high traffic volume periods. Drivers should allow for extra travel time and use caution when traveling through work zones. Flaggers may be present in the roadway directing traffic and traffic may be stopped for short periods of time. Drivers are encouraged to be patient and courteous to other drivers. 

PennDOT has numerous projects taking place in the State College area and is aware of the frustration road work can create. This work is part of the North Atherton Street project that is taking place through 2019 with phased work zones stretching from Aaron Drive to Park Avenue. Work will include the relocation of numerous utility lines, relocation of sewer and water lines, drainage improvements, curbing, sidewalks, ADA ramps, traffic signal upgrades, new concrete median and paving.

To help make decisions about travel, motorists are encouraged to “Know Before You Go” by visiting www.511PA.com. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1.

For regional updates on Twitter, follow www.twiiter.com\511PAStateCOLL.

Media Contact: Marla Fannin (814) 765-0423


Update 08/24/2018

Update through August 31 on North Atherton Street Project

The Pennsylvania Department of Transportation (PennDOT) wants to inform the public about the work that will continue on North Atherton Street.

Please note, on Monday, August 27, drivers should expect MAJOR travel delays due to the work to update the traffic patterns in the various work zones. There will be one lane ONLY for inbound traffic and one lane ONLY for outbound traffic. Flaggers will be at each signalized intersection between West Aaron Drive and West Cherry Lane to assist with traffic flow. Drivers are encouraged to choose alternate routes on Monday or build in extra travel time into their schedules.

People traveling on North Atherton Street can expect the following delays through Friday, August 31:

  • From West Aaron Drive to West North Hills Place – Work in this area will consist of upgrading the existing drainage system. While the contractor is working, traffic will be reduced to a single lane for outbound traffic. Due to the turning lane being used for outbound traffic, left turns will be restricted through the length of this work zone. Signage indicating “No Left Turn” will be in place.
  • From West North Hills Place to West Cherry Lane – Work in this area will consist of upgrading the existing drainage system. Traffic control will feature daylight lane closures and will have at least one travel lane available in each direction. Due to the turning lane being used for outbound traffic, left turns will be restricted through the length of this work zone. Signage indicating “No Left Turn” will be in place.
  • From West Cherry Lane to West Hilcrest Avenue – Verizon will be performing utility relocations in this area. Traffic control will consist of daylight lane closures maintaining traffic on at least one lane in each direction.

* There will be NO LANE CLOSURES on Friday, August 31 due to a Penn State University home football game and Monday, September 3, due to the Labor Day holiday. 

Travel delays could occur because of the lane closures. Flaggers will be present in the roadway directing traffic. Traffic may be stopped for short periods of time. Drivers are reminded to use caution when traveling through the work zones. Do not follow construction equipment into the closed lane. All work is weather and schedule dependent.

This work is part of the North Atherton Street project that is taking place through 2019 with phased work zones stretching from Aaron Drive to Park Avenue. Work will include the relocation of numerous utility lines, relocation of sewer and water lines, drainage improvements, curbing, sidewalks, ADA ramps, traffic signal upgrades, new concrete median and paving.

To help make decisions about travel, motorists are encouraged to “Know Before You Go” by visiting www.511PA.com. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1.

For regional updates on Twitter, follow www.twiiter.com\511PAStateCOLL.

Media Contact: Marla Fannin (814) 765-0423


Update 07/27/2018

Weekend Work Scheduled on North Atherton Street Project

The Pennsylvania Department of Transportation (PennDOT) wants to inform the public about the work that will continue on North Atherton Street. Please note there is some work scheduled for Saturday, July 28, and Sunday, July 29.

People traveling on North Atherton Street can expect the following delays through Friday, August 3:

  • From West Aaron Drive to West North Hills Place – Work in this area will consist of upgrading the existing drainage system. While the contractor is working, traffic will be reduced to a single lane for outbound traffic. Due to the turning lane being used for outbound traffic, left turns will be restricted through the length of this work zone. Signage indicating “No Left Turn” will be in place.
  • From West North Hills Place to West Cherry Lane – Utility contractors will install a new sewer line. Traffic control will feature daylight lane closures and will have at least one travel lane available in each direction. The contractor will be working during the daylight hours this weekend, Saturday, July 28 and Sunday, July 29.
  • From West Cherry Lane to West Park Avenue – Verizon will be performing utility relocations in this area. Traffic control will consist of daylight lane closures maintaining traffic on at least one lane in each direction.

Travel delays could occur because of the lane closures. Flaggers will be present in the roadway directing traffic. Traffic may be stopped for short periods of time. Drivers are reminded to use caution when traveling through the work zones. Do not follow construction equipment into the closed lane. All work is weather and schedule dependent.

This work is part of the North Atherton Street project that is taking place through 2019 with phased work zones stretching from Aaron Drive to Park Avenue. Work will include the relocation of numerous utility lines, relocation of sewer and water lines, drainage improvements, curbing, sidewalks, ADA ramps, traffic signal upgrades, new concrete median and paving.

To help make decisions about travel, motorists are encouraged to “Know Before You Go” by visiting www.511PA.com. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1.

For regional updates on Twitter, follow www.twiiter.com\511PAStateCOLL.

Media Contact: Marla Fannin (814) 765-0423

 Update 07/19/2018

PennDOT Issues Atherton Street Update through late-July

The Pennsylvania Department of Transportation (PennDOT) wants to inform the public about the work that will continue on North Atherton Street.

People traveling on North Atherton Street can expect the following delays through late-July:

  • From West Aaron Drive to West North Hills Place – Work in this area will consist of upgrading the existing drainage system. While the contractor is working, traffic will be reduced to a single lane for outbound traffic. Due to the turning lane being used for outbound traffic, left turns will always be restricted through the length of this work zone. Signage indicating “No left turn” is in place.
  • From West North Hills Place to West Cherry Lane – Utility contractors will install a new sewer line. Traffic control will feature daylight lane closures and at least one travel lane available in each direction. The contractor will be working during the daylight hours this weekend, Saturday, July 21 and Sunday, July 22.
  • From West Cherry Lane to West Park Avenue – Verizon will be performing utility relocations in this area. Traffic control will consist of daylight lane closures maintaining traffic to at least one lane in each direction.

Travel delays could occur because of the lane closures. Flaggers will be present in the roadway directing traffic. Traffic may be stopped for short periods of time. Drivers are reminded to use caution when traveling through the work zone. Do not follow construction equipment into the closed lane. All work is weather and schedule dependent.

This work is part of the North Atherton Street project that is taking place through 2019 with phased work zones stretching from Aaron Drive to Park Avenue. Work will include relocation of numerous utility lines, relocation of sewer and water lines, drainage improvements, curbing, sidewalks, ADA ramps, traffic signal upgrades, new concrete median and paving.

To help make decisions about travel, motorists are encouraged to “Know Before You Go” by visiting www.511PA.com. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1.

For regional updates on Twitter, follow www.twiiter.com\511PAStateCOLL.

Media Contact: Marla Fannin (814) 765-0423


Update 07/10/2018

PennDOT Issues Atherton Street Update through mid-July

The Pennsylvania Department of Transportation (PennDOT) wants to inform the public about the work that will be underway on North Atherton Street.

People traveling on North Atherton Street can expect the following delays through mid-July:

  • From West Aaron Drive to West North Hills Place – Work in this area will consist of upgrading the existing drainage system, installing new curbing and sidewalk and placing topsoil. The middle turning lane will remain closed throughout this section. However, due to the Central Pennsylvania Festival of the Arts, there will always be two lanes of travel for both inbound and outbound traffic from Wednesday, July 11, to Friday, July 13. Left turns will always be restricted through the length of this work zone. Signage indicating “No left turn” is in place.
  • From West North Hills Place to West Park Avenue – Utility contractors will continue performing relocation work. Traffic control will feature daylight lane closures and at least one travel lane available in each direction.

Travel delays could occur because of the lane closures. Flaggers will be present in the roadway directing traffic. Traffic may be stopped for short periods of time. Drivers are reminded to use caution when traveling through the work zone. Do not follow construction equipment into the closed lane. All work is weather and schedule dependent.

This work is part of the North Atherton Street project that is taking place through 2019 with phased work zones stretching from Aaron Drive to Park Avenue. Work will include relocation of numerous utility lines, relocation of sewer and water lines, drainage improvements, curbing, sidewalks, ADA ramps, traffic signal upgrades, new concrete median and paving.

To help make decisions about travel, motorists are encouraged to “Know Before You Go” by visiting www.511PA.com. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1.

For regional updates on Twitter, follow www.twiiter.com\511PAStateCOLL.

Media Contact: Marla Fannin (814) 765-0423

Update 06/07/2018

PennDOT Issues Atherton Street Update for June 11 to Mid-June

Delays likely; motorists reminded to use patience and courtesy

The Pennsylvania Department of Transportation (PennDOT) wants to inform the public about the work that will be underway on North Atherton Street.

People traveling on North Atherton Street can expect the following delays from Monday, June 11 through mid-June:

  • From West Aaron Drive to West North Hills Plaza –  Work in this area will consist of upgrading the existing drainage system, waterline and sewer line. Crews will implement a long-term traffic pattern that closes the right lane heading south, and when contractor is not working two lanes will remain open for inbound and outbound traffic. Note, all left turns will be restricted in this work area.
  • Aaron Drive and North Atherton Intersection – An intermittent detour will be in place at this intersection and drivers that need to access Aaron Drive will be directed to Viaro Boulevard.
  • From West North Hills Plaza to West Park Avenue – Utility contractors will continue performing utility relocation in the area. This will require daylight lane closures and at least one travel lane available in each direction.

Travel delays could occur because of the lane closures. Flaggers will be present in the roadway directing traffic. Traffic may be stopped for short periods of time. Drivers are reminded to use caution when traveling through the work zone. Do not follow construction equipment into the closed lane. All work is weather and schedule dependent.

This work is part of the North Atherton Street project that is taking place through 2019 with phased work zones stretching from Aaron Drive to Park Avenue. Work will include relocation of numerous utility lines, relocation of sewer and water lines, drainage improvements, curbing, sidewalks, ADA ramps, traffic signal upgrades, new concrete median and paving.

To help make decisions about travel, motorists are encouraged to “Know Before You Go” by visiting www.511PA.com. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1.

For regional updates on Twitter, follow www.twiiter.com\511PAStateCOLL.

Media Contact: Marla Fannin (814) 765-0423


Update 05/04/2018

PennDOT Issues Atherton Street Update for First Two Weeks of May

Work will be suspended for Penn State graduation. 

The Pennsylvania Department of Transportation (PennDOT) wants to inform the public about the work that will be underway on North Atherton Street. People traveling on North Atherton Street can expect the following through mid-May:

  • Monday, April 30, to Friday, May 4: 
  • A detour will be in place on Aaron Drive that will direct traffic to Vairo Boulevard.
  • The contractor will be paving the Aaron Drive and North Atherton Street intersection.
  • Monday, May 7, to Friday, May 11:
  • Temporary signal polls will be installed on North Atherton Street at the West Aaron Drive and West North Hills Place intersections.
  • Monday, May 14, to Friday, May 18:
  • The contractor will be installing sewer lines in the West North Hills Place and North Atherton Street intersection.

Travel delays could occur because of the lane closures. Flaggers will be present in the roadway directing traffic. Traffic may be stopped for short periods of time. Drivers are reminded to use caution when traveling through the work zone. Do not follow construction equipment into the closed lane. All work is weather and schedule dependent.

This work is part of the North Atherton Street project that is taking place through 2019 with phased work zones stretching from Aaron Drive to Park Avenue. Work will include relocation of numerous utility lines, relocation of sewer and water lines, drainage improvements, curbing, sidewalks, ADA ramps, traffic signal upgrades, new concrete median and paving.

To help make decisions about travel, motorists are encouraged to “Know Before You Go” by visiting www.511PA.com. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1.

For regional updates on Twitter, follow www.twiiter.com\511PAStateCOLL.

Media Contact: Tim Nebgen (814) 765-0423

Update 03/28/2018

PennDOT Offers Update Through Mid-April for Atherton Street Project

The Pennsylvania Department of Transportation (PennDOT) wants to inform the public about the work that will be underway on North Atherton Street. People traveling on North Atherton Street can expect the following through mid-April:

  • On Wednesday, March 28, night work will take place to install waterline across Atherton Street at several locations. Work hours are set to begin at 7 p.m. and will continue through 5 p.m. Thursday, March 29.
  • No work will be performed by the contractor on Friday, March 30 in observance of Good Friday and the Easter holiday weekend. Columbia Gas may be working on Friday.
  • Water and sewer line replacement continues from Aaron Drive to Blue Course Drive. Water and sewer line replacement work will advance to Park Avenue throughout the construction season as work zones become available upon completion of utility contractor’s work. Lane closures will be associated with these operations, with lane closures alternating as needed.
  • During work at the Aaron Drive intersection, there will be a detour that routes all traffic to Martin Street.
  • Starting April 2, Verizon is expected to begin relocation of overhead lines from Blue Course Drive to Cherry Lane. Lane closures will be associated with these relocations.

Travel delays could occur because of the lane closures. Flaggers will be present in the roadway directing traffic. Traffic may be stopped for short periods of time. Drivers are reminded to use caution when traveling through the work zone. Do not follow construction equipment into the closed lane. All work is weather and schedule dependent.

This work is part of the North Atherton Street project that is taking place through 2019 with phased work zones stretching from Aaron Drive to Park Avenue. Work will include relocation of numerous utility lines, relocation of sewer and water lines, drainage improvements, curbing, sidewalks, ADA ramps, traffic signal upgrades, new concrete median and paving.

To help make decisions about travel, motorists are encouraged to “Know Before You Go” by visiting www.511PA.com. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1.

For regional updates on Twitter, follow www.twiiter.com\511PAStateCOLL.

Media Contact: Marla Fannin (814) 765-0423


Update 03/15/2018

PennDOT Offers Look-Ahead for Atherton Street Project

The Pennsylvania Department of Transportation (PennDOT) wants to inform the public about the work that will be underway on North Atherton Street. People traveling on North Atherton Street can expect the following:

  • Beginning Tuesday, March 20, crews will be removing the center concrete median at the intersection of North Atherton and Aaron Drive. This work will establish the traffic control for the project and is expected to take 1 to 2 days. North and south passing lanes and the center turning lane will be closed during this work. No left turns will be permitted along this stretch of North Atherton during this work.
  • Monday, March 26, crews will begin water and sewer line replacement throughout the project. Work will begin at the Aaron Drive intersection and continue to Blue Course Drive. Water and sewer line replacement work will advance to Park Avenue throughout the construction season as work zones become available upon completion of utility contractor’s work. Lane closures will be associated with these operations, with lane closures alternating as needed. There will also be some night work associated with these operations.
  • Ongoing utility relocation work from Blue Course Drive to Park Avenue. Lane closures will be associated with these relocations. Utility work will continue through June. You can view that full announcement below.

Travel delays could occur because of the lane closures. Flaggers will be present in the roadway directing traffic. Traffic may be stopped for short periods of time. Drivers are reminded to use caution when traveling through the work zone. Do not follow construction equipment into the closed lane. All work is weather and schedule dependent.

This work is part of the North Atherton Street project that is taking place through 2019 with phased work zones stretching from Aaron Drive to Park Avenue. Work will include relocation of numerous utility lines, relocation of sewer and water lines, drainage improvements, curbing, sidewalks, ADA ramps, traffic signal upgrades, new concrete median and paving.

To help make decisions about travel, motorists are encouraged to “Know Before You Go” by visiting www.511PA.com. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1.

For regional updates on Twitter, follow www.twiiter.com\511PAStateCOLL.

Media Contact: Marla Fannin (814) 765-0423


Update 02/28/2018 

Update on North Atherton Street Utility Work

The Pennsylvania Department of Transportation (PennDOT) wants to inform the public about the various utility work that is underway on North Atherton Street. People traveling on North Atherton Street can expect the following:

  • Closure of the northbound travel lane (right lane) from Blue Course Drive to Park Avenue for West Penn Power and Verizon utility work.
  • In early March, closure of northbound and southbound passing lanes (left lanes) from Blue Course Drive to Cherry Lane for Columbia Gas utility line relocation work.

Drivers should allow for extra travel time and be alert for lane shifts between Cherry Lane and Park Avenue during the utility work detailed above. All work is weather and schedule dependent.

This work is part of the North Atherton Street project that is taking place through 2019 with phased work zones stretching from Aaron Drive to Park Avenue. Work will include relocation of numerous utility lines, relocation of sewer and water lines, drainage improvements, curbing, sidewalks, ADA ramps, traffic signal upgrades, new concrete median and paving.

To help make decisions about travel, motorists are encouraged to “Know Before You Go” by visiting www.511PA.com. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1.

For regional updates on Twitter, follow www.twiiter.com\511PAStateCOLL.